Running RAC in a Virtual Environment

I was in a discussion at an Oracle Meetup this week, and the subject of RAC in a virtualized environment – specifically Oracle Virtual Machine (OVM) – came up.
Here’s a couple of points which were discussed.

pingtarget

There was a lack of awareness of a common problem, which has a solution built-in to Oracle 12.1.0.2 Grid Infrastructure and later. In a virtualized environment, the network components are also virtualized. Sometimes, network failures on the host may not be raised up to the guests. As a result, the guest O/S commands can fail to detect the network failures and the Virtual NIC remains up. Grid Infrastructure (GI) will not perform a VIP fail-over as it can’t see the failure despite the network being unavailable.

To resolve this, Oracle has added an option of a “pingtarget” for each public network defined in GI. This will perform a keep-alive to a external device, usually something like the default gateway. This is just like the heartbeat on the cluster interconnect.

Before

srvctl config network

Network 1 exists

Subnet IPv4: 192.168.0.160/255.255.255.224/eth1, static
Subnet IPv6:
Ping Targets:
Network is enabled
Network is individually enabled on nodes:
Network is individually disabled on nodes:

The default gateway makes a good ping target. For this IP and subnet, it’s 192.168.0.161

srvctl modify network -k 1 -pingtarget 192.168.0.161

After

srvctl config network

Network 1 exists

Subnet IPv4: 192.168.0.160/255.255.255.224/eth1, static
Subnet IPv6:
Ping Targets: 192.168.0.161
Network is enabled
Network is individually enabled on nodes:
Network is individually disabled on nodes:

All safe!

Server Pools

A second item we discussed was the Server Pools in OVM. Each RAC guest should be on a different host, otherwise you have not eliminated that as a Single Point Of Failure. A second less obvious SPOF is the Server Pool disk.

A Server Pool is a filesystem LUN (and IP address prior to release 3.4) used to group a logical collection of servers with similar CPU models, within which we can create and migrate VM guests. For a RAC installation, each RAC node should be within a different server pool, as well as on different physical hardware.

ovs

In this image, RAC nodes within the same cluster should be created within each server pool. This configuration can safely support a 2 node cluster despite having 4 servers, with one node created in “OVS-Pool-2” on server “ovs02“. The second node should be in “OVS-Pool-1″ and can be on “ovs01“, “ovs11” or “ovs12“.

It is possible to live migrate guests between these 3 servers.

 

 

 

 

 

Why ITIL CAB’s do not work as expected

ITIL (Information Technology Infrastructure Library) does work. It works very well and is becoming more and more widely adopted, but does not always work the way that management thinks it works.

The basic premise of ITIL is to put structure and process around the business of running IT. It is a collection of guiding principles which, if appropriately adopted into a company will help run the IT function in a reasonable process-driven fashion. It’s largely common sense, which helps.

However, after lots of experience with all of the different aspects of ITIL I have decided that it doesn’t really work the way management think it does. This is especially relevant to Change Management.

The premise behind Change Management is that technical staff are prevented from making non-Standard changes to the IT systems without prior authorisation from all relevant stakeholders.

Where this falls down is 2 fold.

– The definition of Standard change needs to be very carefully identified, documented and locked-down. It never is, leading to techies making personal decision about what constitutes standard change. This definition is always enthusiastically elastic, until something snaps when it will become frustratingly draconian (for a while).

– The stakeholders rarely understand the nature and true impact and risk of the changes taking place, so the CAB must accept the opinion of the techie (see above). The net result of a Change Advisory Board (CAB) is to authorise the technical staff to make change whilst putting the burden of responsibility for the change onto the management. Not the techie. If the changes goes wrong, then it is fault of the approving manager for not assessing the risk correctly, or for approving the change to take place at the wrong time or in the wrong way. However, the techie gets off scott free in all of this.

As long as the process is followed, we can get away with murder.